By System Admin on June 11, 2026
Beginner

BISMALLAH — Kistet Procurement & Inventory INSHA'ALLAH

This guide covers how Kistet Engineering & Trading manages procurement of instruments, equipment, and supplies through DOBiz SmartERP.

Procurement Workflow

Material Request → Purchase Order → Purchase Receipt → Purchase Invoice → Payment

Step 1: Creating a Material Request

A Material Request (MR) is an internal document that initiates the procurement process.

Who Can Create

  • Field Engineers (for project materials)
  • Technical Manager (for equipment)
  • COO/Finance (for office supplies)

How to Create

  1. Go to DOBiz SmartERP > Stock > Material Request
  2. Click + Add Material Request
  3. Fill in:
  4. Title — Brief description (e.g., "VW Piezometers for Gololcha Dam")
  5. Company — Kistet Engineering & Trading
  6. Request Type — Purchase
  7. Project — Select the project (if project-related)
  8. Required By — When materials are needed on site
  9. Add Items table:
  10. Item Code — Select from item list
  11. Qty — Quantity needed
  12. Required Date — When each item is needed
  13. Description — Any specifications
  14. Click Save

Material Request Status

Status Description
Draft Being prepared
Open Submitted, awaiting approval
Approved Approved, ready for PO
Ordered Converted to Purchase Order
Partially Received Some items received
Received All items received

Step 2: Creating a Purchase Order (PO)

The Purchase Order is sent to the supplier to place the order.

How to Create (from Material Request)

  1. Open the approved Material Request
  2. Click Create > Purchase Order
  3. The system pre-fills items from the MR
  4. Verify:
  5. Supplier — Select from suppliers (Geokon, Campbell Scientific, ORBINOX)
  6. Currency — USD (for imports) / ETB (local)
  7. Exchange Rate — If foreign currency
  8. Delivery Date — Expected delivery
  9. Terms — Payment terms (e.g., 50% advance, 50% on delivery)
  10. Add any additional charges:
  11. Shipping Charges
  12. Insurance
  13. Customs & Duties
  14. Click Save > Submit

How to Create (directly)

  1. Go to DOBiz SmartERP > Buying > Purchase Order
  2. Click + Add Purchase Order
  3. Fill in supplier, items, dates, and terms
  4. Click Save > Submit

PO Statuses

Status Description
Draft Not yet finalized
To Bill and Receive Active, awaiting delivery and invoice
To Bill Received but not invoiced
To Receive Invoiced but not received
Completed All items received and invoiced
Closed Order cancelled or closed

Step 3: Purchase Receipt

When goods arrive, record them in the system.

  1. Go to DOBiz SmartERP > Stock > Purchase Receipt
  2. Click + Add Purchase Receipt
  3. Select the related Purchase Order
  4. Verify items and quantities received
  5. Enter:
  6. Warehouse — Where items are stored (e.g., "Kistet Addis Ababa Warehouse")
  7. Serial Nos — For trackable items (instruments have serial numbers)
  8. Batch No — If applicable
  9. Click Save > Submit

Step 4: Purchase Invoice

Record the supplier's invoice in the system.

  1. Go to DOBiz SmartERP > Buying > Purchase Invoice
  2. Click + Add Purchase Invoice
  3. Select the related Purchase Order or Purchase Receipt
  4. Verify items, quantities, and prices
  5. Enter Taxes and Charges:
  6. VAT (15% in Ethiopia)
  7. Withholding Tax (if applicable)
  8. Import Duties (for imported goods)
  9. Click Save > Submit

Step 5: Payment

Process payment to the supplier.

  1. From the Purchase Invoice, click Create > Payment
  2. Verify amount
  3. Select Payment Type — Wire Transfer, Bank Transfer, etc.
  4. Select Bank Account — Company's bank account
  5. Click Save > Submit

Inventory Management

Items (Products)

Key item groups for Kistet:

Group Examples
Instrumentation Vibrating Wire Piezometers, Inclinometers, Crackmeters
Hydromechanical Hydraulic Gates, Stoplogs, Penstocks
Services Installation, Commissioning, Training
Equipment Data Loggers, Cables, Readout Boxes
OEM Parts Spare parts for instruments

Creating a New Item

  1. Go to DOBiz SmartERP > Stock > Item
  2. Click + Add Item
  3. Fill in:
  4. Item Code — e.g., "VW-PIEZO-4500S"
  5. Item Name — e.g., "Model 4500S Vibrating Wire Piezometer"
  6. Item Group — e.g., "Instrumentation"
  7. Unit of Measure — e.g., "Nos", "Set", "Meter"
  8. Brand — e.g., "Geokon"
  9. Supplier — Default supplier
  10. Standard Buying Rate — Purchase price
  11. Standard Selling Rate — Sales price
  12. Click Save

Warehouse Stock

  • Each warehouse tracks quantity on hand
  • Stock updates automatically with Purchase Receipts and Stock Entries
  • Check stock levels: DOBiz SmartERP > Stock > Stock Balance

Key Suppliers

Supplier Products Payment Terms
Geokon (USA) Vibrating wire sensors, dataloggers L/C or T/T
Campbell Scientific (USA) Data acquisition systems L/C or T/T
ORBINOX (Spain) Gates, stoplogs, penstocks L/C or T/T
Geomation (USA) Remote monitoring software Annual license

Procurement Tips

  • Plan ahead — Imported items take 60-90 days
  • Use Material Requests — Don't create POs directly
  • Track serial numbers — All instruments should be serialized
  • Attach documents — Quotations, invoices, customs docs to the PO
  • Check budget — Before creating MR, check project budget
  • Import process — Coordinate with finance for customs clearance